ICCO Completes 76.2 km Section III of Beji–Jangara–Wushishi Road
International Consolidated Contractors Offshore SAL Ltd (ICCO) has completed the Design and Construction of Section III of the Beji–Jangara–Wushishi Road in Niger State. The section runs 76.2 km , from km 0+000 to km 76+200. The Ministry of Works and Infrastructural Development issued the Certificate of Completion on 8 May 2025 , reference MOW/CPC/2025-048. This article sets out who awarded the contract, what it covered, and what the Ministry's certificate says about how the work was done. The rest of this series looks at each part of the road in more detail. Key facts Project: Design and Construction of Section III of the Beji–Jangara–Wushishi Road, Niger State Contractor: International Consolidated Contractors Offshore SAL Ltd (ICCO), sole contractor Contract No.: MOW/CDB-GB/SIII-22 Length: 76.2 km (km 0+000 to km 76+200) Contract price: ₦33,298,345,042 (final value, including variations, unchanged) Duration: 36 months; work began...